West Pennant Hills Culvert

Published: Sep 2019


Project: Culvert

Location: West Pennant Hills, NSW

Profiles: 155mm & 275mm

Project Details: 11m length (5 cells)

Advantages of Dincel design

  • All materials moved around and on-site without crane (original design required 250tonne crane)

  • Lead time reduced from 18 weeks to immediate availability 

  • Project not affected by rain

Benefits to Contractor

  • Cheaper, quicker and easier construction

  • Allowed second stage subdivision work to proceed much earlier 

  • Improved cash flow

Dincel Used

Culvert

155mm & 275mm Profiles

Gallery click to view full size


Case Studies

Gundagai Sewerage Treatment PlantMay 2020

“I was sceptical to begin with, mainly because I hadn’t used the product before and I was old school.” David said. “When the engineer told me, you didn’t have to use too much bracing and it held itself mainly, I was very sceptical so that’s when we decided to have a look at it.”

West Pennant Hills CulvertSep 2019

Culvert in West Pennant Hills. 11m length (5 cells)

Design, Supply & Install
for all your Civil Infrastructure needs.

Let's get started Organise a product presentation
Design, Supply and Install for all your Civil Infrastructure needs